Tag Archives: vat-construction

VAT: When is the building of a house complete? (And why is it important?)

By   11 June 2019

Completion of a residential dwelling

A technical point which comes up surprisingly often and seems innocuous is: when is a building “complete”? The following case is helpful, and I thank Les Howard for bringing it to my attention.

The date that the construction of a dwelling is deemed to be complete is important for a number of reasons. The issue in the case of Mr and Mrs James was whether certain works could be zero rated via the VAT Act Schedule 8 Group 5 Item 2 (The supply in the course of the construction of a building designed as a dwelling…) or as HMRC contended, they were the reconstruction or alteration of an existing building and the work should be standard rated.

Background

The James used a contractor to plaster the entire interior of their house in the course of its construction. However, the work was demonstrably defective to such an extent that the James commenced legal proceedings. A surveyor advised that all of the old plaster needed to be hacked off and replaced by new plastering installed by a new firm. The stripping out and replacement works took place after the Certificate of Completion had been issued.

The James claimed input tax on the house construction via the DIY Housebuilders’ Scheme.

Technical

HMRC refused the James’ claim to have the remedial work zero-rated because, in their view, the re-plastering works amounted to the reconstruction or alteration of the house which was, when the supplies were made, an “existing building”. They proffered Note 16 of Schedule 5 which provides that “the construction of a building” does not include “(a) … the conversion, reconstruction or alteration of an existing building”.

They stated that zero-rating only applied if the work formed part of the construction of a zero-rated building. They had previously decided that the work of snagging or correction of faults carried out after the building had been completed could only be zero-rated if it was carried out by the original contractors and correction of faults formed part of the building contract. When the snagging is carried out by a different contractor, the work is to an existing building and does not qualify for zero rating.

The James stated that the Customs’ guidelines on snagging do not take into account extraordinary circumstances. Their contention was that the re-plastering works were zero rated because they had no choice but to engage the services of a different contractor other than the one who carried out the original works.

Decision

The judge found for the appellant – the re-plastering works were zero rated.

There was a query as to why The James applied for a Certificate of Completion before the plastering was completed. In nearly all cases such a certificate would crystallise the date the building was complete.

The reasons were given as:

  • the need for funds. The James could not remortgage the house without the certificate and they needed to borrow a substantial amount
  • they could not reclaim VAT under the DIY Housebuilders’ Scheme until the Certificate of Completion had been issued
  • they were aware that the building inspector was beginning to wonder why the building works were taking such a long time
  • they needed the house assessed for Council Tax which could only happen when the certificate had been issued
  • the Certificate was issued as part of the procedure required by the Building Act 1984 and the Building Regulations of 2000

These reasons were accepted by the judge.

Despite the respondents stating that:

  • for the reasons given above
  • the fact that the James had been living in the house for some time
  • they had obtained the Certificate of Completion
  • the new plastering work had been done by the new plasterer such that the house had been constructed before supply of the new plasterer’s services had been made
  • the house was an “existing building”

the judge was satisfied that in the circumstances the new plastering work was supplied in the course of the construction of the building as a dwelling house and that there was no reconstruction or alteration of an existing building in the sense contemplated by Note (16) to Group 5 Schedule 8.

He observed that the Certificate of Completion records that the substantive requirements of the Building Regulations have been satisfied. But to the naked eye the old plasterwork was obviously inadequate and dangerous ad he could not possibly consider that the construction project had finished until the new plasterwork was installed. The James’ construction project was to build a new dwelling house. Plasterwork of an acceptable standard was an integral part of the construction works. The new plasterwork was done at the earliest practicable opportunity.

Commentary

Care should be taken when considering when the completion of a house build takes place. There are time limits for DIY Housebuilders’ Scheme clams and clearly, as this case illustrates, usually work done to a house after completion does not qualify for zero rating. So, if the owner of a house is thinking of, say, building a conservatory for example, it is more prudent in VAT terms to construct it at the same time as a new house is built, and certainly before completion.

I would say that the appellant in this case achieved a surprisingly good result.

VAT: Extent of zero rating for a construction by a charity

By   9 October 2017

Latest from the courts

In the First Tier Tribunal (FTT) case of The Trustees of Litton & Thorner Community Hall the issue was whether certain construction works were a completion of an initial build or whether they were an extension or an annex to a pre-existing building. And if an annex, whether it was capable of functioning independently from the existing building and whether there is a main access to the annex.

Background

The appellant began construction of a hall in 2008. It was intended that the hall would be available for a school to use and also for it to be available at for village use and other activities, such as by local youth clubs and a scout group. There was no dispute that the original construction was zero rated via VAT Act 1994, Schedule 8, Group 5, item 2  (The supply in the course of the construction of a building designed for a relevant charitable purpose).

A decision was made to install ground source heat pumps to feed the heating system. However the space occupied to accommodate the system meant that there was insufficient storage space in the hall. So at the time of construction, but before planning permission was obtained, it was decided with the builder that a steel joist should be incorporated within the east wall of the hall in order to facilitate the necessary support and access when the envisaged storage facility was added.  The additional planning permission was granted in November 2011, three years after building work commenced. The facility was eventually able to be used when work was completed in 2014. The delay was caused (not surprisingly) by funding issues. It was the VAT treatment of work relating to the addition of the storage area which was the subject of the appeal, with HMRC considering that it was either standard rated work to the building or was a standard rated extension to it.

Technical background

The provisions relevant to the appeal are VAT Act 1994, Schedule 8, Group 5, Notes 16 and 17. It is worthwhile taking a moment to consider these in their entirety:

Note 16

For the purpose of this Group, the construction of a building does not include

(a ) the conversion, reconstruction or alteration of an existing building; or

(b) any enlargement of, or extension to, an existing building except to the extent the enlargement or extension creates an additional dwelling or dwellings; or

(c) subject to Note (17) below, the construction of an annexe to an existing building.

Note 17

Note 16(c) above shall not apply where the whole or a part of an annexe is intended for use solely for a relevant charitable purpose and;

(a) the annexe is capable of functioning independently from the existing building; and

(b) the only access or where there is more than one means of access, the main access to:

(i) the annexe is not via the existing building; and

(ii) the existing building is not via the annexe.

The Appeal

The Trustees appealed on two separate and distinct bases:

(1) That the additional building was the completion of the original building and neither an extension nor an annex to it. It was their case that the temporal disconnect between the two building processes must be seen in the factual context, with particular reference to the decision to put in a lintel to allow the building to be completed when additional monies and planning permission were available. Additionally, alongside this fact was that the appellant was a non-commercial organisation and so things could not progress as expeditiously as they might have done if those things were being undertaken by a commercial organisation.

(2) The second basis is that, in any event, the additional building is zero rated by reference to paragraphs 16(c) and 17 of Group 5 to Schedule 8. It was the appellant’s case that the additional building is an annex intended for use solely for relevant charitable purposes and it meets the conditions set out in paragraph 17(a) & (b).

Decision

The FTT decided that the work was subject to zero rating. Not only was it part of the original construction (albeit that there was a significant time period between the building original work and the work on the storage area) but also, even if the storage area is considered as being separate, it was ruled that, on the facts, it was an annex rather than an extension, so it also qualified for zero rating on this basis.

Commentary

The date a building is “completed” is often an issue which creates significant disputes with HMRC, not only for charities, but for “regular” housebuilders. I have also encountered the distinction between an annex and an extension representing a very real topic, especially with academy schools. Even small changes in circumstances can create differing VAT outcomes. My advice is to seek assistance form a VAT consultant at the earliest stage possible. It may be that with a slight amendment to plans, zero rating may be obtained in order to avoid an extra 20% on building costs which charities, more often than not, are unable to reclaim.

Links to what we can offer to schools here, and charities here

Additionally, our offering to the construction industry here

VAT on residential developments

By   20 February 2015

Should work on existing residential property have the same VAT treatment as new build housing? 

The UK cannot create a new zero rate, however, should, say, the reduced rate apply to extensions/redevelopment?

And if so, where should the line be drawn?

Article from Property Week here